The Ontario Energy Board gave Enbridge Gas a conditional section 95(2) exemption from obtaining leave to build about two kilometres of gas line in Merrickville-Wolford. The board’s September 29, 2026 decision, EB-2025-0323, considered the $3.4-million project eligible because cost was the only trigger for leave and the estimate fell within the regulatory range above $2 million and up to $10 million.
The ministry delegated procedural consultation to Enbridge. The Algonquins of Ontario raised concerns about fisheries, cumulative impacts and drilling fluid. Enbridge promised a spill response plan and funded review and archaeological participation. It also engaged the Algonquins of Pikwakanagan First Nation and the Mohawk Council of Akwesasne.
The board found the process proportionate to the risks and the Crown’s duty met for this exemption. Enbridge still needs other permits and must implement environmental recommendations and continue engagement. The exemption ordinarily lapses after 12 months unless construction begins.
Enbridge’s project page lists a potential 2027 start, conditional on approvals.