NWT board permits Taltson repairs but leaves cost recovery undecided
NTPC must explain inspection timing and work apparently begun before approval, and implement a strategy to extend the surge tank’s life.
Section
Administrative tribunal decisions and judicial-review developments across Canada
223 stories
NTPC must explain inspection timing and work apparently begun before approval, and implement a strategy to extend the surge tank’s life.

The permit relaxes vehicle and staffing limits while restricting repairs to the operator’s own buses.

The majority approved a three-cent monthly increase, while two dissenters wanted to await broader reforms; an August order implemented the rate.

Rail journeys did not exempt the company’s local truck movements from licence requirements.

The CNSC’s April 2026 reasons explain its earlier authorization for additional reactor units, with hold points, contractor corrections and limits on delegated approval.

The board upheld council’s balancing of housing choice and neighbourhood impacts under the town’s particular planning policies.

A $6,000 penalty and four-year extension formed part of an approved Ontario securities settlement.

The Ontario Energy Board approved $132,865 in retroactive recovery but refused other account changes and ordered an independent review.

Ontario’s tribunal emphasized that director and officer prohibitions also cover non-reporting issuers.

The commission ordered the full $950 deposit returned with interest, finding no reliable basis for damage estimates or an added electricity charge.

A delayed registered letter did not restart the appeal period after statutory public notice, but the commission urged the minister to address the unfairness.

The regulator rejected a small-provider exemption but delayed onboarding until the first request and retained response and workload limits.

B.C.’s Environmental Appeal Board required better emissions evidence and a fresh regulatory assessment, while rejecting claims that pollution and injuries had been proved.

Obtaining provincial water approval did not eliminate the need for final municipal authorization.

The adjudicator upheld the refusal but rejected the town’s objection to his jurisdiction.

Facility Association won approval for an overall 11 per cent increase, with reporting requirements and a conditional direction to seek a decrease if specified tariffs were removed.

B.C.’s Environmental Appeal Board ruled that statutory groundwater rights can support an appeal even when the domestic user does not hold a separately issued licence.

Newfoundland and Labrador tribunal ordered $196 after requiring proof of financial loss.

The labour board found the new student-support role closer to faculty-association work, while clarifying how competing unions’ claims should be assessed.