The Island Regulatory and Appeals Commission gave Maritime Electric early approval to rebuild an aging distribution line between Kinross and Vernon River. The project’s estimated cost was $1.635 million.

In its August 6, 2026 order UE26-08, the regulator found enough evidence to approve the project separately from the utility’s broader capital budget. The rebuild replaces about 6.8 kilometres of existing line serving about 414 customers. It is intended to maintain reliability, not expand the system.

Maritime Electric sought the decision in July so it could use contractors and resources already assigned during the 2026 construction season. Contractor labour accounted for $947,000 of the estimate. The commission found the estimate consistent with the work proposed.

The order did not approve any other projects in the approximately $102.6-million application. The capital-budget docket treats any eventual request to change rates as a separate matter. The early approval did not itself change customer rates or confirm that construction had finished.